Enviro Infra Engineers shares are likely to remain in focus on September 10 after the company received a Letter of Intent (LoI) from Tata Power Renewable Energy for an EPC turnkey project worth ₹224.19 crore, including GST.
Through its step-down subsidiary Suyog Urja (SUL), the company has received the LoI for executing EPC turnkey works for NTPC’s 180 MW wind power project at Parli in Maharashtra. The project is scheduled to be completed by March 31, 2027.
The scope includes wind turbine generator (WTG) foundation works, balance of plant (BoP) works and construction of a 33 kV transmission line.
Under the WTG foundation package, SUL will undertake civil foundation works for 58 wind turbine generators, including associated reinforcement steel and geotechnical requirements.
For the BoP works, the subsidiary will develop an approximately 39-acre storage yard, manage the right of way (ROW) for material movement and construct access roads, pathways and crane pads, along with other civil and infrastructure works.